A level instrument creates a horizontal line of sight. A staff reading tells you how far a point lies below that line. Start from a point with a known elevation.

Beginner-friendlyFree · No accountOne worked example + one practice problem
01

What the formula is saying

Add backsight BS to known level RLA to find the line-of-sight elevation. Subtract foresight FS to find the new point level RLB.

RLB = RLA + BS − FS

Read the symbols in plain language

RLA
Known reduced levelm
BS
Backsightm
FS
Foresightm

Sort out the units first

All three inputs are in metres on the same vertical datum. BS and FS are staff readings, not horizontal sight distances.

02

Let’s solve one together

Read the given values, follow each operation, then check what the result means.

RLA · Known reduced level
100 m
BS · Backsight
1.5 m
FS · Foresight
0.8 m
  1. Find the line-of-sight elevation

    The staff reaches from the known point up to the horizontal sight line.

    (100) + (1.5) = 101.5 m
  2. Subtract the reading at the new point

    A larger staff reading means the point is lower below the same sight line.

    (101.5)-(0.8) = 100.7 m
Answer100.7 m

Does this worked answer make sense?

BS − FS = 0.7 m, so the new point is 0.7 m higher than the known 100 m point.

03

Now try your own values

Change a value or its unit. The same method will show your calculation, step by step.

English, Arabic and Persian digits are supported. The steps convert inputs to the formula’s base units.

Results update only when you calculate. The lesson example above stays unchanged.

04

Your turn — check your understanding

Use these new values. Work it out first, then check your answer.

RLA · Known reduced level
50 m
BS · Backsight
1.2 m
FS · Foresight
1.7 m

Find: a level from backsight and foresight

For repeating decimals, use at least four significant figures. Accepted rounding tolerance: 0.05% of the expected value; zero uses an absolute tolerance of 10⁻¹².

A hint, not the answer

Add backsight BS to known level RLA to find the line-of-sight elevation. Subtract foresight FS to find the new point level RLB.

All three inputs are in metres on the same vertical datum. BS and FS are staff readings, not horizontal sight distances.

Show the full practice solution

Compare the steps with your work; revealing a solution does not mark the lesson complete.

  1. Find the line-of-sight elevation

    The staff reaches from the known point up to the horizontal sight line.

    (50) + (1.2) = 51.2 m
  2. Subtract the reading at the new point

    A larger staff reading means the point is lower below the same sight line.

    (51.2)-(1.7) = 49.5 m
Answer49.5 m

Avoid the common trap

Adding both readings is wrong: add backsight, subtract foresight. Do not confuse line-of-sight elevation with the tripod’s physical height.

When this method applies — and when it does not

One ideal instrument setup with upright staff readings. Real levelling also needs closure, observation and instrument checks; those are not performed here.

For study and understanding, not approval of a real structure, site operation or design. Apply the correct standard, National Annex and professional review to actual engineering work.

One idea understood. Keep going.

This optional checkmark is saved only in this browser. It is your own progress note, not a certificate.

Sources & further reading

References open in a new tab and explain the underlying principles. The teaching text and examples here are SimpleFlick’s own; the source organisations have not endorsed this calculator.

Lesson updated: · Worked examples checked against the implemented formula; not an independent engineering certification.

Menu